At BSM, safety is a top priority and we never compromise on it. Unfortunately, there are accidents outside our company that have resulted in the loss of lives; let’s ensure these are not repeated on our fleet.

Fatal Fall From Ladder

fall_from_ladder.png

A ship, enroute to Los Angeles was preparing for the USCG inspection. The C/O instructed the Bosun to de-rust and paint the corroded turnbuckle and the securing pin for the free-fall lifeboat. Bosun assigned this job to an AB.

No work permit was issued as the work site was at one metre height and secured by railings. The C/O carried out only a verbal risk assessment. He had instructed the crew not to carry out any work aloft due to moderate rolling.

fall_from_ladder_2.jpg




While performing the task, the AB observed that the forward hook for the free-fall lifeboat needed lubrication. AB requested the Bosun to assist him by steadying a portable ladder to reach the forward hook. The height from the deck to the forward hook was 4.8 metres. The ladder was 5 metres long.

The AB climbed up the ladder neither securing it nor using any PPE. The Bosun tried to hold the ladder in place however, was not able to control it. The AB fell along with the ladder and ended up motionless on the deck. He was tragically pronounced dead 3 hours later.

Consequences

  • Fatality
  • Delays
  • Reputation of the company

Causes

  • Failure to follow procedures:

- Lack of risk assessment and work permit – Although the working aloft procedures in the company’s SMS required a risk assessment and work permit to be prepared, these were not completed before starting work

- Use of unsafe equipment – The portable ladder was inappropriate for the task. The poor condition of the ladder feet meant both the legs were not in contact with the deck. The fact that ladder was not safely secured probably contributed to the ladder slipping and the AB falling off it

- Lack of PPE – The AB did not use proper PPE while climbing the ladder, as required by company procedures (e.g. safety helmet with chin strap, safety harness and fall arrester). This would have offered some protection to the AB when he fell and may have reduced the severity of his injuries:

  • Inadequate monitoring, casual approach:

- Lack of intervention – The Bosun could have prevented the incident if he had stopped the job rather than assisting the AB to steady the ladder. Stop Work card provide crew members with the responsibility and obligation to stop work in case of an apparent unsafe condition or behaviour.

  • Complacency – Completing a task not requiring a work permit, led the AB to assume that it would be acceptable to also lubricate the hook without a permit. Complacency can lead to shortcuts from established safe work procedures to save time and effort, but it can also lead to undesirable consequences.

fall_from_ladder_3.jpg

Lessons learnt

  • Make use of the “Stop work card” when a colleague or a group of colleagues do not follow safe working practices.
  • Strictly comply with company procedures of risk assessment, work permit etc. while working at heights.
  • Ensure that all equipment is in good condition and used properly. Portable ladders must:

- Be secured properly.

- Be placed on stable surfaces at correct angles (between 60 deg and 75 deg. from the horizontal).

- Have anti-skid foot cap.

- Extend at least 1 m above the upper landing area.

  • Always use appropriate PPE while working.

Death Due to Burn Injuries

The C/E decided to clean the “Waste Oil Settling Tank” (WOST) to repair a malfunctioning level indicator. He carried out the RA for the tank cleaning operation and assigned the job to the 2/E and 3/E.

The 2/E drained the WOST by gravity to the “Bilge Separator Oil Tank” (BSOT) through the drain valve. The 3/E turned the wire wheel of the scale reduction device on the top of the WOST and reported it was working. The 2/E opened the self-closing water drain valve and observed only a small quantity coming out. Based on above indications, the 2/E concluded that the WOST was empty.

The 3/E climbed on a folding ladder to remove the manhole cover located at a height of about two metres. He removed most of the nuts from the manhole except four nuts diagonally across from each other. He then loosened the last 4 bolts by half a turn. As there was no further oil leakage, he loosened the remaining nuts further. Without removing the nuts, he pulled the cover which detached from the seat. The hot oil of approx. 86°C splashed from the manhole bottom onto the 3/E.

The 2/E pulled away the 3/E and removed his coverall soaked with the hot oil. Crew brought the 3/E to the ship’s hospital and gave him first aid. He had sustained serious burns to various areas of his body. The Master requested a medevac through the local agent. The 3/E himself boarded the helicopter which took him to the local hospital. However, the 3/E died 12 days later at the hospital due to septic shock.

burn_injuries.png

Tank manhole at two meters height

Consequences

  • Fatality
  • Delay
  • Loss of company reputation

Causes

  • Improper risk assessment: Not identifying the potential hazards related to the unknown quantity of hot sludge remaining in the tank due to the malfunctioning level gauge.
  • Making assumptions: Despite the experience and professional knowledge, involved engineers assumed the tank was empty which led to an unexpected hazard exposure and injury.
  • Toolbox talk was not carried out before commencing the job.
  • Inadequate Planned Maintenance System (PMS): It did not address the foreseeable jamming of the level gauges with sludge oil.
  • Protective clothing: The 3/E was wearing a common cotton coverall. This provides only limited protection against the penetration of hot liquid and transfer of heat to the skin.
  • Temperature of the sludge oil: Although the heating of the tank had been closed, the adjacent tank was continually heated. As a result, the content was indirectly heated to about 86˚C through conduction.
  • Sounding pipe: The tank was not fitted with a sounding pipe as an alternative means when the level gauge malfunctioned. Although not a requirement, this would have allowed the two engineers to verify the contents of the tank.

Lessons Learnt

burn_injuries_2.png

  • Carry out a thorough risk assessment before starting any unplanned job.
  • Always conduct a toolbox meeting with the involved personnel discussing the findings of the RA and necessary precautions to prevent any accident.
  • Include an appropriate and regular regime for cleaning the tank in PMS, this would have helped avoid the need for this unplanned and hazardous task.
  • Use appropriate PPE for the job. The investigation identified that an ISO 11612 compliant coverall could have possibly provided better protection to the 3/E from hot oil.
  • Follow safe practice for the opening of the manhole.

- The common practice identified in the investigation report to safely remove this type of manhole cover is to:

- Remove all nuts except four crosswise.

- Slightly loosen the four nuts by no more than half a turn.

- Tighten the jackscrews to detach the cover from the seat.

- If a leakage is observed, the cover may be easily secured back by loosening the jackscrews and re-tightening the nuts.

- If no leakage is observed, loosen the nuts another half turn and tighten the jackscrews.

- If there is still no leakage, continue to loosen the four crosswise nuts and remove the cover.

Source: Britannia P&I

RELATED BSM Insight

The potential of Carbon Capture and Storage for the shipping industry
The potential of Carbon Capture and Storage for the shipping industry

Carbon Capture and Storage (CCS) is a safe and efficient way to handle emissions and meet climate targets. And it offers beneficial opportunities for the shipping industry in gaining new business and reducing its own carbon footprint, Johan Lillieskold, Gas Solutions Specialist at Schulte Group, is convinced.

EU ETS: It's time to act
EU ETS: It's time to act

On 1 January 2024, shipping officially joined the European Union’s Emission Trading System (EU ETS). With it emerged a comprehensive set of responsibilities, accompanied by significant financial implications for shipping companies who, for the first time, are included in a market-based measure such as EU ETS. The increased level of interaction between the European Commission and the shipping industry means a novelty for both parties - and an ongoing learning process.

Unlocking operational synergies between yachting and commercial shipping
Unlocking operational synergies between yachting and commercial shipping

The superyacht industry has been developing significantly over the recent years, especially since 2020. Today, the total fleet worldwide is at 12,500 yachts over 24m seeing explorer yachts and multihulls growing in popularity and the attractiveness of very large yachts unbroken, despite other predictions. BSM Yachting has entered this market with an innovative approach.

Revolutionising seafarer training: breaking boundaries
Revolutionising seafarer training: breaking boundaries

Driven by the ever-evolving landscape of the shipping industry, BSM continuously updates the training programmes offered by its Maritime Training Centres (MTC), ensuring they remain at the forefront of industry standards. One example for this dynamic is the MTC’s response to the challenges of the global pandemic resulting in the development of not only highly specialised but also flexible and DNV-approved SIRE 2.0-related courses.

The next challenge in procurement
The next challenge in procurement

Founded in 2017 as a joint venture, GP General Procurement Company Limited (GenPro) is an independent procurement company. GenPro's objective is to negotiate framework supply agreements with international ship suppliers, ensuring BSM’s customers benefit from optimal prices for maritime products and services worldwide. In addition, the company actively advocates for the establishment of more sustainable supply chains.

Nourishing the body and soul of seafarers
Nourishing the body and soul of seafarers

The role of food onboard commercial vessels has always been an essential aspect of seafarers' lives. Throughout the years, there have been significant changes in the requirements and standards related to food onboard commercial vessels, particularly in terms of hygiene, food quality and the importance placed on these aspects for seafarers. For 30 years, Seachef Hospitality Services has been providing catering and hospitality services in the maritime world. Time to look back.

BSM is ready to go for EU ETS
BSM is ready to go for EU ETS

Carbon Compliance Management

There are only a few days to go until EU’s Emission Trading System (EU ETS) kicks in for the shipping industry from 2024. Bernhard Schulte Shipmanagement (BSM) has developed a comprehensive range of carbon compliance and EU ETS management services designed to support owners and operators mastering the complex regulation requirements and to reduce their carbon footprint and related costs.

Careers at BSM